Construction Progress Report #9

October 24, 2011

Site work is wrapping up for the season. The 1st layer of asphalt was installed for erosion control. The asphalt will allow the water to flow in the necessary directions into the functioning storm system. All the water collected onsite flows to a sediment pond in the north east corner of the property. The water will settle and then continue down the ravine in 30” inside diameter concrete pipe to the Nehalem. Landscapers are onsite getting ready parking lot planters read for topsoil, and working on getting the multi-use field leveled and seeded.