Construction Progress Report #8

September 29, 2011

The 50,000 gallon underground tank (mentioned in an August posting) has been installed. Only a small portion of it remains uncovered between the west classroom wing and the kitchen. It will be used to help cool the building via the radiant flooring system. The window installation will begin next month. The building is beginning to look quite impressive from the outside as much of it has been painted already, but that is nothing compared to being inside and seeing just how big it is going to be. It will be a wonderful addition to our community.