The construction of the building is split up into 4 “Sectors” or areas labeled A, B, C, & D in the construction plans. The concrete slabs have been poured in sector C (main gym) and A & D (Classroom wings). P&C is starting the last footings in sector B, which is the cafeteria, stage, and commons area. This last sector is critical because not only is there a lot of underground piping work in the kitchen that is important to get in the correct spot, it also houses the mechanical area. The main center for mechanical is a 16×8x9 ft vault buried in the ground. This vault will contain pumps that are connected to the boiler and to the radiant in floor heating pipes throughout the building.