Construction Progress Report #11

November 21, 2011

The site is set for winter. There is grass growing where both the baseball and softball fields will be as well as the main playground to the north of the school. The road across the fields to the retention pond is complete as well as the back road that leaves the school property in the northeast corner onto Texas Ave. This will be used primarily for fire access to the back of the school and to get to the current house that will be eventually used as the district office and partner space.