Construction Progress Report #10

November 10, 2011

West Wing Classroom Framing

The west classroom wing (see photo in ‘read more’) is in full swing. Framing is complete on the 1st level, skylights installed, and roofing complete. The concrete openings are getting ready for window frames and glass. It’s the contractors goal to get the building “dried in” as soon as possible. It is important to get the openings closed to keep the water out, and keep heat in the building for the drywall mud to dry. The steel for the two main stairways between the first and second floors is in and the concrete base will be poured soon. You can really begin to see the layout of the school come together.